79 Seddon Road, Morden, SM4 6ED
Project Value
£1.5m
Project Overview
This scheme was the demolition of an existing building, and the erection of two new build properties in replacement. QS Support have been involved from the beginning advising of initial cost advice, through to full contract support.
Benefits of our Support
QS Support were able to move swiftly into locating the correct contractor for the client and executing contracts in a timely manner to enable works to commence expediently on site.
Pre-Contract Services Provided
Detailed cost plans
Invitation to tender
Tender procurement
Tender reporting and analysis
Contracts
Post-Contract Services Provided
Valuations and Payment Certificates
Cost Control
Variation and Change Control
Final Account
Dispute Resolution Services Provided